Upgrade an existing edge gateway to improve gateway capacity and performance.

If you are upgrading an edge gateway with Full configuration and High Availability enabled to Full-4 configuration, ensure that ESXi has at least 8 CPUs.

1

Click the Manage & Monitor tab and click Organization VDCs in the left pane.

2

Double-click the organization virtual datacenter name to open the organization virtual datacenter.

3

Click the Edge Gateways tab, right-click the edge gateway name, and select Upgrade.

Edge gateways with Compact configuration are upgraded to Full configuration, and edge gateways with Full configuration are upgraded to Full-4 configuration.

If you upgraded a Compact gateway to Full configuration, you can repeat the upgrade process to upgrade to a gateway with Full-4 configuration.